PROJECT DESCRIPTION
The project involves construction of a new indoor tennis practice facility and will be built on the University's Southwest Campus adjacent to the new FSU Morcom Aquatics Center. The completed facility will house (4) - (6) NCAA/USTA compliant practice courts with support spaces and may also operate to provide for competition in times of inclement weather. It is anticipated that the facility will share some site amenities, such as parking, access drives, and storm water facilities with the Aquatics Center. Construction materials and methods are anticipated to facilitate training and competition for highly competitive events and will likely include covered or enclosed long span construction, natural ventilation, and indirect lighting, while promoting identity of the facility as a part of Florida State University. Commensurate with the University's goal to support environmentally responsible construction, this project will seek LEED certification. It is anticipated that a GMP will be requested at completion of 50% construction documents, and the Construction Manager may also be asked to help develop cost models for future facility upgrades. At the University's discretion and dependent upon available funding, the Construction Manager may be requested to provide a GMP to include facility upgrades. Construction is anticipated to begin March 2009 and be complete by January 2010.
PROJECT BUDGET
The current project budget is $5,000,000, with a construction budget of $3,900,000.
SELECTION CRITERIA
Firms will be evaluated in the following areas: experience and ability, including successful completion of related projects, past experience, past performance, bonding capacity, preconstruction services experience including value engineering and detailed estimating, construction services experience including record keeping/administrative ability, critical path scheduling expertise, cost control ability, quality control capability, qualifications of the firm's personnel, staff and consultants. The firm should demonstrate experience in the following areas: construction of tennis facilities and other long span facilities for indoor sports; LEED certified construction.
SELECTION COMMITTEE
Kim Ball, Project Manager
Liz Maryanski, Assoc. VP for Student Affairs
Joe Nosari, Assoc. VP for Academic Affairs
Chris Rettkowski, Athletics Facilities and Event Management
Bernie Waxman, Associate Athletics Director
| CM SELECTION SCHEDULE |
| Submittals due |
October 7, 2008 |
| Short list meeting |
October 20, 2008 |
| Final interviews |
November 4, 2008 |
| Selection recommendation approval (approximate date) |
November 10, 2008 |
| Contract negotiation (approximate date) |
November 13, 2008 |
|
BUILDING PROGRAM
Detailed project information is presented in the building program. Applicants may arrange to purchase a copy of the program by contacting Target Copy, 635 W. Tennessee Street, Tallahassee, telephone 850-224-3007. (The building program is also included on the Facilities Design & Construction web page.)
GENERAL INFORMATION
- All applicants will be notified of the results of the short listing via the FSU Office of Facilities Design & Construction website: www.fpc.fsu.edu. Interview times for finalists will be posted at this website address, as well.
- The Selection Committee will make a recommendation to the University President. Final ranking of firms will be posted on the Facilities Design & Construction web site. Upon approval by the President, negotiations will be conducted in accordance with Section 287.055, Florida Statutes.
For additional information or questions, please contact:
Kim Ball, Project Manager
Facilities Design & Construction
107 Mendenhall Building A
The Florida State University
Tallahassee, FL 32306-4152
Telephone: (850) 644-1290, Fax: (850) 644-8351
kstrobel-ball@admin.fsu.edu
|
Last Updated:
09/09/2008
© 2008 FSU